1. Fix the fusion splicer to install the heating end, place the fusion splicer on the rack, install ppr pipe , and fitting to tighten it, usually the smaller one at the front end.
2. Power on
Turn on the power supply (note that the power supply must have a grounding protection wire), the green indicator light is on and the red indicator light is off, indicating that the fusion splicer enters the automatic control state and can start operation. Note|: In the state of automatic temperature control, the red and green lights will alternately light up, which means that the fusion splicer is in a controlled state and does not affect the operation.
3. Welding pipe
Use a pipe cutter to cut the plastic ppr pipe vertically, push the pipe and pipe fittings into the fusion splicer die without rotating at the same time, and operate as required by the following table. After the heating time is reached, immediately remove the pipe and pipe fittings from the die at the same time without rotating quickly The ground line is evenly inserted to the required depth, so that a uniform flange is formed at the joint.