Construction preparations for thermally welded PE water supply pipes

Jun 28, 2022

Leave a message


The preparations for the construction of the hot-melt PE water supply pipe are as follows: check that the specifications of the PE pipe are consistent with the specifications of the fixture of the hot-melt machine, and install the fixture of the hot-melt machine; adjust the PE pipe/PE water supply pipe to keep it at the same height as the fixture, and do a good job Fixing measures; set the temperature of the heating plate from 200 to 230 °C (the heating temperature is based on the temperature marked on the hot-melt machine); connect the power supply, heat the heating plate, turn on the oil pump switch, and the milling cutter used for cutting PE water supply pipes, observe whether normal operation.